Hydraulic Braces and Temporary Works

 

Discover our experience supporting utilities and infrastructure projects in the UK.

ContractorGold Max, Newtonstewart Ltd, Red Parrot, Gallagher Group Ltd.

LocationSouthern England.

Walton-on-Thames, Surrey

Contractor: Gold Max

A new industrial park pumping station required drainage infrastructure. As part of the project, we installed two large manhole rings using GU13 interlocking Sheet Piles, working in difficult ground conditions with a high-water table.
The Conquip 300 Brace being used at Walton-on-Thames, with Gold Max.
The Conquip 300 Brace being used at Walton-on-Thames, with Gold Max.

    Littlehampton, Hampshire

    Contractor: Newtownstewart Ltd

    We installed a large crate system on the main A259 bypass in Littlehampton, with live traffic in close proximity. Complex works, traffic streams and night deliveries were navigated to accommodate the client’s needs.
    The Conquip 300 Brace being used at Littlehampton, Hampshire, with Newtownstewart Ltd.
    The Conquip 300 Brace being used at Littlehampton, Hampshire, with Newtownstewart Ltd.
    Image

      Greater London

      Contractor: Red Parrot

      We provided a responsive excavation design service, ahead of the installation of a new concrete holding tank at a major London water treatment works site.
      The Conquip 300 Brace being used at Greater London, with Red Parrot.

        Hills, Oxfordshire

        Contractor: Gold Max

        We provided a brace system to enable the installation of a large pump station at 8.5m deep on the project in North Oxford.
        Image

          Northfleet, Kent

          Contractor: Gallagher Group Ltd

          We created the temporary works design at this electronic waste facility construction site. The highly complex designs, which required CAT 3 checks, were required in order to excavate the ground for three new underground drainage tanks, in very challenging ground conditions (a mix of gravel, sand and clay). The in-house team also supervised the installation of three levels of 300 Brace to each earthwork support system.
          The Conquip 300 Brace being used at Northfleet Kent, with Gallagher Group Ltd
          The Conquip 300 Brace being used at Northfleet Kent, with Gallagher Group Ltd
          Image

            Trench Shoring

            From design to hire service, delivery and support.
            A man in a hole supported by a Conquip 300 Brace

            Ground Engineering Brochure

            Download and read a full copy of our Ground Engineering brochure.