Excavation Made Easy for Morrisroe

48 Carey Street

Safe, cost-effective and easy muck removal with system of two cycling BulkX skips.

Contractor

Morrisroe

Location

Location Name


Challenge

Morrisroe were responsible for a large phase of this prestigious project, including excavation and the basement superstructure.

One particular issue they faced was the final part of the excavation. Conquip got involved to help provide a solution.

Morrisroe identified that they needed a safe, cost-effective and easy way to excavate the remaining muck from site. We recommended the BulkX System, a solution designed by Conquip for efficient excavation and waste removal.

bulkx withfree standing gantry configuration used on Carey Street project
bulkx skip being loaded by an excavator
bulkx with free standing gantry
bulkx discharging to truck

Solution

Conquip helped Morrisroe to choose the right specification of BulkX System.

Two skips were utilised, of 3000 litres and a 4000 litres capacity. By cycling the skips, the site team achieved faster muck away.

The system permitted Morrisroe to excavate quietly and efficiently, without needing temporary works designs or further permission from the council for alternative schemes.

The BulkX System only required a one lane road closure, which was already in place to accommodate site welfare cabins.


Feedback

"We couldn’t have achieved this in any other way."

Banksman at Carey Street, Morrisroe