We have detected that you are visiting from United States.

Please click here if you would prefer to visit our United States website.

X

My Quote

No products in the Quote.

Persimmon Homes Development

 

Temporary works design & shoring kit supply for housing development in Somerset

ContractorCJL Construction Ltd for Persimmon Homes Severn Valley

LocationSomerset, UK

The Project

CJL Construction Ltd took on the installation of deep drainage and utilities during the groundworks phase for a Persimmon Homes development of 80–100 homes. For this project, CJL brought in Conquip to deliver a temporary works service and supply a range of shoring equipment.

Conquip delivered its ‘Standard Shoring Solutions’ temporary works design, while CJL hired a variety of Trench Boxes, Lightweight Trench Boxes, and Manhole Boxes. They also used ancillary trench access and safety equipment. On-site, the team operated an Excavator Pipe Laying Hook to unload and manoeuvre pipes, and they deployed Road Plates to manage the uneven terrain.

The Challenge

Ensuring trench safety is critical on groundworks projects and becomes difficult without the right equipment. To maintain safety during trench excavation across the site, the experienced CJL team installed Conquip’s shoring boxes. This setup allowed them to lay foul water and storm water drainage pipes across the 1.5-hectare site in Yatton, near Weston-super-Mare.

CJL also needed to unload and manoeuvre heavy concrete pipe sections from delivery trucks into position—another key challenge on the site.

The Solution

With a fast-paced 12-week schedule to maintain, CJL requested a temporary works design before starting on-site, enabling the creation of a detailed planning schedule.

Conquip’s design supported trench excavation to a depth of 2.3 metres in heavy clay soil. The included shoring boxes enabled CJL to lay the pipes safely and efficiently. Thanks to their robust construction, Conquip’s shoring boxes allowed the team to install them quickly while ensuring a safe working environment for operatives in the trench.

CJL used the Trench Access Platform and the Davit Fall Arrest System to guarantee safe access in and out of the trench via the ladder. The Excavator Pipe Laying Hook allowed the team to manoeuvre pipe sections with speed and precision, improving overall site productivity.

Conquip’s adaptable equipment range met the site’s specific needs, accommodating different pipe sizes and applications to provide CJL with a complete end-to-end shoring solution. Click here to find out more.

Project feedback

“We’ve been working with Conquip on four or five of our sites that need shoring boxes. This one in Yatton is for our client, Persimmon Homes. Having just moved over to Conquip as our shoring partner, we’re very impressed. The temporary works and design team are quick and efficient and the ordering process and customer service for the boxes we needed was seamless – you don’t have to give them very long to get the order here on time. On this project, they have delivered exactly what they said.”

Graham Cheeseman | Drainage Construction Manager, CJL Construction

DON’T MISS OUT!

It’s time to join our revolution to cut costs, save time, and improve safety in construction. Sign up to our emails to make sure that you don’t miss out on new product launches, industry insights and best practice updates. Sign Up